KAI resumes LAH deliveries as 2027 aircraft ramp faces engine-supply scrutiny
Korea Aerospace Industries expects to deliver more than 50 aircraft in 2027 and over 90 in 2028, but engine-component delays have trimmed near-term KF-21 output.

Korea Aerospace Industries (KAI) has resumed deliveries of its Light Armed Helicopter (LAH) after resolving a quality issue in the engine manufacturing process, the company said, as it prepares to ramp up total aircraft deliveries to more than 50 units in 2027 and more than 90 in 2028.
The delivery outlook was reported by Bloter, citing a Hanwha Investment & Securities report titled “KAI Sacheon site CFO-led meeting review” published on Nov. 19. The ramp is tied to domestic deliveries of initial-production KF-21 Boramae fighters and increased FA-50 export deliveries to Poland and Malaysia, according to the report.
KAI said it can normally deliver its 2027 contracted volume despite recently raised concerns about engine-component supply, Bloter reported. However, the Defense Acquisition Program Administration (DAPA) cut its 2027 first-quarter KF-21 delivery outlook from four aircraft to one because delivery of the U.S.-supplied F414 engine accelerator component was delayed, according to Bloter.
On the LAH program, KAI said the engine quality issue had been resolved and deliveries had resumed. Delayed LAH volumes from this year will be reflected in future delivery schedules, Bloter reported.
iM Securities said KAI had delivered 7 of the 30 LAH units planned for this year in the first half and estimated that only 2 to 3 additional units would be delivered by year-end after deliveries resumed in November, according to Bloter. Around 20 LAH units could be deferred because of the delivery disruption, Bloter reported.