Daejeon High Court cuts Hanwha Aerospace's ADD late-delivery penalty but rejects company's government-fault argument
The appellate court reduced the penalty from $9.03 million to $7.06 million, while attributing the 2019 accident, work stoppage and delivery delay to the company rather than the government.

The Daejeon High Court's 2nd Civil Division ruled that the Agency for Defense Development (ADD) must pay Hanwha Aerospace $1.96 million (2.61 billion won) in a lawsuit seeking return of alleged unjust enrichment, Newsis reported on Oct. 6.
Hanwha Aerospace filed the lawsuit against ADD in March 2024, arguing that a $9.03 million (12.02 billion won) late-delivery penalty was improper, according to Newsis.
The underlying incident was a February 2019 explosion at Hanwha Aerospace's Daejeon site that killed three workers and led to a work-suspension order that was lifted in phases over about six months, Newsis reported.
The first-instance court found the work-suspension order was issued for site preservation and prevention of recurrence, and that a one-month special inspection after the accident found 114 safety and health violations, Newsis reported.
Korea Daily, carrying JoongAng Ilbo, reported that the court rejected Hanwha Aerospace's argument that the delivery delay was the government's fault, but reduced the penalty from 12.02 billion won to 9.41 billion won.
Both Hanwha Aerospace and ADD filed appeals against the appellate ruling, Korea Daily reported, carrying JoongAng Ilbo.